Preventive excavation Team

In the team has Archaeologists specialist working and responsible for doing the excavation.

Archaeological Preventive Excavation in the Project of the Development in the Southern Pond of Angkor Wat

The south-pond rehabilitation project was implemented by the Department of Monuments and Archaeology I in an aim to beautify the Prasat Angkor Wat and to enhance its value.

The preventive excavation had to be done before we conducted this project. It is very important to get information about the ancient stratigraphy and the new embankment and then we will see what we can do to rehabilitate.
In 2005, we drew a topographical map of the site and excavated here by opening a 1.20m-by-66m-long trench across the pond from south to north. According to this report, on 3rd February 2007 we continued to do the excavation by opening another pit at the north-east corner of the pond to collect more information.
Based on the result of these excavations, we can divide the stratigraphy into 3 phases:
- 1st phase is 13 pond laterite steps and the basement of these steps.
- 2nd phase is very big clay layer.
- 3rd phase is a new embankment or the mud of the pond bed; the average thickness is 20cm or 400m³.

During the excavations, the preventive excavation team has discussed on the site with H.E Ros Borath, Mr. Eric LLOPIS (an archaeologist in FSP Project) and Mr. Rachid EL HAJAOUI (a French consultant to the preventive excavation team). Then, a hypothesis has been put forward concerning the draught of reservoirs in Angkor Wat as well as the whole region of Angkor. On the other hand, if we take out the new embankment or the mud of the pond floor which is 20cm deep in average, it will affect the entire area and we will not benefit from the rehabilitation project at all.

Finally, we decided to conserve this new muddy embankment for research purposes to allow us to get more data about the environment in the Angkor area and proposed to look after this pond by refilling the reservoirs with water every season.

 

 


Excavation activities

 


Laterite steps were found

Archaeological excavation at Angkor Thom’s moat
(on the north of south gate)

Since 2007 up to now, Preventive excavation team cooperated with EFEO (under the direction of Prof. Jacques Gaucher) to excavate at Angkor Thom’s moat. The aim was to understand the structure of Angkor Thom wall “Jayakiri” and laterite step on both sides of the moat. This excavation is still processing, so we do not get the results yet.

 


Excavation activities

Preventive Excavation at the construction site of the Woman Development Centre

On 24th January 2007, the Archaeological Unit conducted a preventive excavation on Woman Development Centre’s construction site, Ministry of Woman’s Affairs. It is located in Ploung Village, Leng Dai Commune, Angkor Thom District, Siem Reap Province.
The team unearthed 10 pits. We found a mound and a trace of canal (probably an ancient canal) existence from the north to south, situated in the west of the construction site.
After the excavation, we assumed this site has a low archaeological potential. Thus, we could give a chance for the construction, but we permitted them to dig only from 50 to 100cm deep and our team proposed to conserve this ancient canal.

 


Excavation activities

Preventive Excavation on five public toilet construction sites

From March to April 2007, the Archaeological Unit conducted a preventive excavation at Prasat Chao Srey Vibol and Roluos. The result of the both sites was confirmed to have a low archaeological potential and we found some potsherds. Due to the finding, the construction of the toilets was allowed. However, the foundation must go down between 50 and 100cm in depth.

The excavation at Taprom, Preah Khan and West Baray is still under way.

 


Excavation activities at Chao Srey Vibol


Back to top

 

 
   
 
© 2005 APSARA This website was built in cooperation with the Swiss Agency for Development and Cooperation